Red Arrow cleanup set to begin Monday

Red Arrow cleanup set to begin Monday

EPA estimates project will take a few weeks; water, equipment must be decontaminated
Red Arrow funding

The Red Arrow Mill clean up will be funded through the following EPA sources. These represent cost ceilings, not fixed pricing.
Superfund Technical Assistance Response Team: $60,000
Special unit of the US Coast Guard that assists On-Scene
Coordinators: $10,000
Emergency Response and Removal Services
(cleanup contractor): $288,000
Contingency costs: $71, 600
Total estimate: $429,600

click here to add your event
Area Events